How to Install a SEKO Metering Pump: Suction Lift, Piping, and Priming
Even a top-tier chemical dosing pump will lose prime, leak at the threads, or siphon uncontrollably if piped incorrectly. Following proper SEKO metering pump installation standards prevents 80% of common startup problems.
This guide outlines the four essential rules from official SEKO installation manuals for suction lift, stress-free piping, discharge valve order, and initial priming.
1. Pump Positioning and Suction Lift Limits
- Prefer flooded suction: Mount the pump below the lowest chemical tank level whenever possible, tapping the tank sidewall
8–10 cmabove the bottom to avoid sludge. Gravity head keeps the pump head flooded and prevents sodium hypochlorite vapor lock. - Keep suction lift under 1.5 m: When top-mounting on a tank lid, keep vertical suction lift within
1.5 mand hang the foot valve vertically underwater. - Mount strictly upright: Always install the pump head with check valves oriented vertically upward so ceramic balls seat properly by gravity.
2. Stress-Free Suction and Discharge Piping Order
Never let rigid metal piping hang from a plastic PVDF or PVC pump head:
- Suction line:
Tank outlet -> Isolation ball valve -> 40–60 mesh Y-strainer -> Flexible union -> Pump suction. Verify every fitting is airtight. - Discharge line order:
Pump discharge -> Safety relief valve (piped back to tank top) -> Pulsation dampener -> Backpressure valve (0.15–0.25 MPa) -> Pressure gauge -> Isolation valve -> Process injection check valve. Never place any shutoff valve between the pump outlet and the relief valve.
3. Electrical Check and Priming
Verify supply voltage (100–240V AC for solenoid models or 380V three-phase rotation on motor units) and wire the low-level tank switch. Set stroke to 100%, open the manual bleed knob counterclockwise until bubble-free liquid flows through the return tube, then close and pressurize.
Conclusion
Flooded suction, stress-free unions, proper relief-before-backpressure valving, and 100% bleed priming keep SEKO metering pump installation trouble-free. Visit Products or Contact Us for valve kits.
FAQ
Can suction and discharge ports be swapped on a SEKO pump?
No. The bottom port with the upward flow arrow is suction, and the top port is discharge. Reversing them locks both check valves shut.
How tight should fittings be threaded into a PVDF pump head?
Hand-tight plus a light quarter-turn with PTFE tape or O-ring unions. Over-tightening with heavy wrenches cracks plastic threads.
Do I need a backpressure valve when dosing into an open atmospheric tank?
Yes. Install a 0.15–0.25 MPa backpressure valve and terminate the line above maximum tank level to prevent siphoning.
What weather protection is needed outdoors?
Mount inside a ventilated rain and sun-shield enclosure so UV exposure and rain do not degrade electronics or overheat bleach.
Do you supply matching PVDF relief and backpressure valves?
Yes, we stock PVC, PVDF, and SS316L backpressure valves, relief valves, Y-strainers, and dampeners.